Heavy Oil/Bitumen Partial Upgrading

image
EADIEMAC Process Plant Modular Skid Mounted Unit
  • Our process team initiated a research project at the Alberta Research Council, now Alberta Innovates, with the objective of developing a way to reduce the requirement for diluent at heavy oil/bitumen well sites.
  • A 1.5 bbl/day pilot plant was designed, built and tested at the Alberta Research Council's facilities in Nisku and Devon to establish the parameters for a field partial upgrader utilizing a visbreaking process.
  • Patent: See original (US#5,110,447 & CAN#1313639)
  • Patent development for improvements to the original process.
  • In a related project, a 200bbl/day used lube oil processing facility, a #2 diesel was output and tested in trucks.
  • Current activites involve the construction and testing of a 2000 bbl/day demonstration plant.
  • This will lead to 10,000 bbl/day modular commercial units.
  • Background
  • Armed with the basic research, engineering designs evolved over several years to fine tune a practical and economical plant.
  • These designs were then put into a complete set of drawings suitable for fabrication.
  • A local Alberta fabricator was able to provide a cost to fabricate the plant within the skid limits.
  • With this information we were able to establish that it was economical to build and operate a field demonstration unit of 2000 bbls/day.
  • The design is scalable to suit modular plants of 10,000 bbls/day or more at site or near site production locations.
  • Meanwhile, our development activities continue with advanced patents to enhance the basic system by separating a portion of the resid on site, as feedstock for higher value uses.
  • The EADIEMAC process is one of a few advanced modular field partial upgrading systems, 100% Canadian owned and developed. It is available to Canada in the event industry decides to incorporate partial upgrading, on site, in a wellhead to tidewater system to enhance pipeline efficiency or governments decide it is of strategic value in Canada's energy future.
The adjacent link takes you to a draft copilot generated technical report.
Report #1 Technical (Click this link)

We use cookies to enable essential functionality on our website and analyze website traffic. For more information, read our Cookies and Privacy Policy.

Your Cookie Settings

We use cookies to enable essential functionality on our website and analyze website traffic. For more information, read our Cookies and Privacy Policy below.

Cookie Categories
Essential

These cookies are strictly necessary to provide you with services available through our websites.

Analytics

These cookies collect information that is used in aggregate and in an anonymized form to help us understand how our website is being used and how effectively our site is performing.